We sat down with Russ Stothers, Product Manager, Investment Lifecycle Management, about the launch of C55 Cost Estimation, one of the modules within our flagship product, Copperleaf C55.

Q: Can you tell us a bit about C55 Cost Estimation?

"C55 Cost Estimation enables organizations to quickly create standardized, comprehensive, and defensible budgetary estimates. By leveraging either unit cost models or a centralized set of parameterized cost models, C55 Cost Estimation produces an estimate that includes capital costs, operating & maintenance costs, and resource demands such as project management hours and labor hours."

Q: Where does C55 Cost Estimation fit in the standard project lifecycle?

"Our clients typically have projects with three major stages:

  • Idea: you need a simple cost estimate (often known as a Class 5 or 4 estimate) to see if the project is worth exploring further
  • Planning: you need a cost estimate that is accurate enough to justify budgetary approval. This is typically a Class 4 or Class 3 estimate
  • Execution: you need a detailed estimate to track project costs, usually referred to as a Class 2 or 1 estimate. It is common to use a bottom-up approach to calculate this detailed estimate

Organizations often struggle to produce good quality budgetary estimates in the idea and planning stages. They typically have to make a trade-off decision between accuracy and effort. Given that the project scope may change after these stages, it doesn’t make sense to spend a lot of effort at this stage. However, there’s also reluctance to approve project budgets if the estimate isn’t refined. C55 Cost Estimation is designed for investment planners that need an accurate estimate during the idea and planning stages."

Q: What is a cost model?

"A cost model is a representation of the costs for a particular asset type. The simplest type is known as a unit cost model, which as the name implies, calculates the costs on a per unit basis such as dollars per meter of cable. You can also have a parameterized cost model, which takes one or more input parameters and uses a decision tree to select a formula to be executed."

Q: What if I don’t have any cost models?

"Copperleaf will work with you to build cost models based on your historical data. It isn’t necessary to have a robust set of complicated models from the get-go. Clients can achieve great results by starting with a core set of simple cost models for the most common type of projects they estimate. C55 Cost Estimation is a continuous improvement process, so over time you can identify opportunities to improve your data collection and enhance your cost models with the latest project actuals."

Q: What are the advantages of using C55 Cost Estimation vs. a separate application?

"C55 Cost Estimation is part of C55, which offers several key advantages:

  • It's integrated with the portfolio planning process, which means you can track your project details and estimates in a single location as they advances from planning through to execution, and then see a rolled-up view at the portfolio level
  • It’s tightly integrated with C55 workflows and your scope change process, making it easy to manage and track changes to your estimates
  • It's seamlessly integrated with the enterprise asset management system. When creating an estimate, you can pull in assets that are impacted by your project, along with their attributes that are needed by the cost model. This makes it extremely easy to estimate the costs of replacing existing equipment"

Q: Who will benefit from this module?

"It's designed for organizations that perform many similar types of investments. When you do the same types of projects, you tend to have a good idea about the underlying costs which makes it easy to create accurate, consistent, and robust cost models. This means that C55 Cost Estimation is highly applicable to clients in asset-intensive industries (e.g. electricity, oil and gas, and water)."

Q: What does a typical estimate include?

"At a high level, the estimate includes four parts:

  1.  Assets: either existing assets in C55 that require an intervention or brand new assets 
  2.  Loadings: project specific modifiers (e.g.  working in a remote area will likely incur additional costs)
  3. Adjustments: manual modifiers to the estimate
  4. Spend Profiles: distribution of the costs over the project duration (e.g. 80% in year 1, 20% in year 2)"

Q: Can you tell us about the C55 Cost Estimation team?

"We are a small cross-functional team of about 8 people that spans development, quality assurance, design, and product management! The team formed in early 2016 to support the development of C55 Cost Estimation in partnership with our client Anglian Water in the UK. We have been working on iterating and improving this capability since then."

Q: Can you share some success stories from your work with Anglian Water? 

"Anglian Water was heavily involved during the design of C55 Cost Estimation. We were able to understand their workflows, propose a design, and iterate based on their feedback. In addition, they participated in beta testing and were able to suggest great improvements to the user interface.

C55 Cost Estimation had significant performance improvements compared to their legacy system. Before, it took Anglian Water over 3 weeks of 24/7 processing time to calculate the costs of intervening on 300,000 estimates. With C55 Cost Estimation, the same volume can be calculated in less than 12 hours. This greatly improved Anglian's ability to model different scenarios under tight timelines for PR19."

Q: What’s next for the module?

"Since it’s a new offering, we are very eager to talk to existing clients and prospects to learn more about their cost estimating challenges and provide a demonstration of how C55 Cost Estimation can help. At Copperleaf, our mission is to develop products that solve problems and maximize value for our clients, so it's really critical to have these conversations and gather input so that we can continue to innovate and improve our offerings."

Watch this video to learn more about C55 Cost Estimation. Marilena Demetriadi and Marina Pomba from Anglian Water share their experience on the implementation and highlight the benefits of C55 Cost Estimation:


Please reach out to us directly to learn more about C55 Cost Estimation. To discover more about our solutions, please visit this page.

About the Author

Copperleaf provides decision analytics to companies managing critical infrastructure. Headquartered in Vancouver, our solutions are distributed and supported by regional staff and partners worldwide. Follow us on LinkedIn.

Follow on Linkedin More Content by Copperleaf Marketing
Previous Article
Webinar: Reducing Risk, Boosting Performance with Asset Management
Webinar: Reducing Risk, Boosting Performance with Asset Management

This webinar explores today's best practices in water asset management and how Anglian Water has implemente...

Next Article
Webinar – Rapid Scenarios: How Leading Utilities are Planning for a Post-Pandemic World
Webinar – Rapid Scenarios: How Leading Utilities are Planning for a Post-Pandemic World

For utilities, ensuring investment plans are keeping pace with the needs of customers and infrastructure is...